What are preliminaries in a construction contract?

read titleRead full title
Published on: 20 November 2017
imgtext

What are prelims?

‘Preliminaries’ in a construction contract, or ‘prelims’, is typically taken to mean the section in the Bills of quantities which groups together items which are necessary for the contractor to complete the works, but will not actually become part of the works, such as scaffolding, plant, water, the cost of power to the site and other site overheads. The preliminaries section also often summarises the contractual terms and services to be provided by the contractor.

The preliminaries are usually found within the first part of the bills of quantities which form part of the Contract Documents in a traditional form of contract, eg the JCT Standard Building Contract. They may also be referred to as ‘general’ items in the bills of quantities, or ‘site overheads’ or ‘field office costs’ (US contracts tend to use these terms).

In JD Wetherspoon v HMRC [2007] UKSPC SPC00657 (a tax case relating to expenditure on fit out works—not reported by UUÂãÁÄÖ±²¥Â®), preliminaries were described as:

‘...necessary costs which are not usually tangibly reflected in the finished works as

Powered by Lexis+®
Jurisdiction(s):
United Kingdom
Key definition:
Preliminaries definition
What does Preliminaries mean?

The section of the bills of quantities that summarises the terms of the construction contract and the general services to be provided by the contractor. Often referred to as ‘prelims’. Will include items such as office overheads, temporary works, telephone and electricity and removal of rubbish.